Poulsbo, WA…The City of Poulsbo City Council is hosting a regular meeting on Wednesday, October 19th. A couple of the major business items on the agenda include the Dogfish Creek restoration grant application and the old city hall demolition change order.
Director of Engineering Kasiniak presented the agenda summary, noting the
Engineering Department has identified a grant funding opportunity to move the
Dogfish Creek Restoration project forward.
Additionally Director of Engineering Kasiniak presented the agenda summary, noting a change
order is needed on the Former City Hall Demolition project to remove approximately
60 cubic yards of contaminated soil from the site. The cost for this additional work
may exceed the 10% threshold ($19,399) for change order and needs council
approval.
The meeting will take place at Poulsbo City Hall located at 200 NE Moe Street.
A copy of the full agenda is available below for viewing